[20th October] We have already renovated 465,0 meters of sewage system in sliplining technology. More information  here!
[15th September] We have already renovated 893,0 meters of sewage system in sliplining technology. More information  here!
[15th May] We have already renovated 1467,90 meters of sewage system in sliplining technology. More information  here!

Wrocław - Korzeniowskiego

Realisation executed in date:
15.06.2014-20.10.2014
In technology: sliplining
Range of works: renowacja kolektora północnego – pierwszy odcinek IV etapu przebudowy
Length of renowation: 465 metre
Average of renowation: 2500 mm
.Description.
 